dpwThe Department of Public Works will be performing pavement operations that will require a temporary closing of Cross St, Railroad Ave, Mendon St, Maple Ave, and Southborough Rd. This work will take place (weather permitting) on July 23, 2015 until completion on August 12th.  The roads will be open to local residents and emergency vehicles. The preliminary detailed schedule is as follows:

Cross Street

7/23 – Pulverize & Grade; 7/27 – Pave Binder & Topcoat

Railroad Avenue

7/23 – Pulverize & Grade; 7/27 – Pave Binder & Topcoat

Mendon Street

8/3 – Cold Plane; 8/10 – Pave

Maple Avenue

8/3 – Cold Plane; 8/11- Pave

Southborough  Road

8/3 – Cold Plane; 8/12 – Pave

Upton Police, Fire and EMS services are aware of the construction.

If you have any questions or comments contact the Department of Public Works Division at (508) 529-3067, between 7:30 a.m. and 3:30 p.m., Monday – Friday or email cpeterson@uptonma.gov

 

4 Comments

  1. Is it all of Mendon Street or just a section? It is a long road and would be helpful to know how much of the street is impacted.

    1. We’re paving from Chestnut Street to the Mendon Town line. Please see the Town’s web site for further information

  2. It would be great if they could add a sidewalk down Maple Street – very busy street with a small shoulder, and near schools too!

Comments are encouraged! If this is your first time commenting (welcome!). Your email is required but not displayed. I ask town officials to use their real names.

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s